Help

  • 右上角的时钟图标会对每道题和所有题计时
  • 右上角的文件夹点击可以打开和关闭当前题号
  • 点击右上角的星星图标 ,所有被收藏的题目均可在“我的”-“收藏”中找到
  • 点击右下角 Next进入下一题。注意:如果你没有做当前题目,你将不可以进入下一题
  • 点击左下角的 QuitEnd Exam 即可退出练习

Close

End Section Review

    你想结束这部分的检查吗?
    如果你点击Yes,你将结束该部分模考。
yes
no

End Exam

    You are about to end your exam

    If you click the Yes button below,your exam will end.
    Are you sure you want to end your exam?
yes
no

Answer Edit Confirmation

    你想更改这个问题的答案吗?
Yes,换答案
No,保留原始答案并回到问题上
注册 注册限时领GMAT/GRE全科PDF备考资料包

欢迎登陆~

验证码
登录
没有账号? 立即注册

欢迎加入~

验证码
注册
已有账号? 立即登录

找回密码~

验证码
提交
记起密码? 立即登录
提交 取消
最新题目

题目内容

收藏
纠错
  • Project
  • Stages and Clusters
  • Status History Reports
At a certain company, successful projects proceed through 8 stages-Stages A through H. An active project is one that is currently in one of these 8 stages. If a stage of a project is completed during a given day, the project is immediately moved to the next stage. At the end of each day, the current stage of each active project is recorded. Some stages require as little as 1 day of work, and none requires more than 3 days of work. A project is said to be delayed if it spends more time at a stage than is required to complete the work. If a project is canceled, the current stage for the day is recorded as Stage X, and the project is no longer considered an active project.
For any given project, the diagram shows the progression of the stages of the project as well as the department of the individuals responsible for each stage. The stages-divided into the initial, intermediate, and final clusters-are each assumed to constitute some nominal fixed percentage (NFP) of the project's lifetime. In the diagram, each cluster percentage is the sum of the NFPs for the stages within the cluster.1538206222454996.png
A status history report-a report containing the daily project status for any project that was active within a given timeframe-is produced by a computer program. Below is the report that was generated at the end of the day today, which is the fifth day of Week 7. The report shows, for example, that Project 75039 began on the second day of Week 6, spent 3 days each in Stages A and B, and has been in its current stage, Stage C, for 3 days.1.1.png

Which one of the following statements is most strongly supported by the information presented in the tabs?
正确答案: D

参考解析

提交我的解析
    知识点概述
    主要考查对项目流程、阶段特性及相关定义的理解与逻辑推理能力,从给定的项目阶段规则等信息中判断各选项的合理性。 解析
    - 选项A:原文未提及项目第一阶段由行政部门人员处理,无依据,排除。 - 选项B:原文没说项目最后阶段由开发部门人员处理,排除。 - 选项C:文中明确表示各阶段耗时最多3天,该选项说阶段F通常持续4 - 6天,与原文矛盾,排除。 - 选项D:因为提到项目成功要经过8个阶段,且各阶段最多3天,同时未提及阶段H有特殊时长,所以阶段H通常持续1天是合理的,当选。 - 选项E:原文只表明项目取消时当前阶段记录为阶段X,未说阶段X紧跟阶段C,排除。

题目讨论 (如果对题目有任何的疑惑,欢迎在这里提出来,大家会帮你解答的哦~)

还没有人评论,赶快抢个沙发~

报告题目错误 ×
请选择错误类型:
请描述一下这个错误:

取消
logo

mofa留学圈
一站式GMAT与GRE在线学习平台

公众号

关注mofa留学圈